Link elements or entire batches from your building model to individual tasks. This allows you to see the progress of the assigned elements directly in the task.
To be able to add and view the nodes or batches, you must be in
the "Project Management" team in the project.
Soon you will be able to find the training video for the article here.
Click Path:
- Workspace Planning > Select Project > Schedules > Open Schedule > "Navigation Bar" > "EMS" > Select / Deselect
- Now select either groups / elements from your node structure and/or batches you have created and click Close. Now the selected nodes/batches are displayed. The status of the elements is indicated by the color of the icon next to the element name.
- If you want to delete all nodes/lots, click Delete. If you only want to delete individual elements instead, click on Select / Deselect and perform the corresponding action.
- If an element is linked to a schedule task, the schedule in the element itself can also be used as status tracker. However, status changes in the element's properties have no effect on the schedule task.
- Double-clicking on an element will take you to the selected element in the building model to view or edit information.