Structure your schedule as detailed and clear as possible by structuring tasks below or above other tasks and thus creating summary tasks.
Soon you will be able to find the training video for the article here.
Click Path:
- Workspace Planning > Select Project > Schedules > Open Schedule
- Select one or more tasks (via multiselect) that you want to indent. Click on the button "Indent" in the left bar. The selected tasks are indented to the task above. This turns the task into a summary task that can be expanded and collapsed.
- The start and end date, the duration and the progress of a summary task are calculated from the sum of the child tasks. These data cannot be adjusted in the summary task.
- If you want to move tasks up in the hierarchy, select the corresponding tasks and click on "Outdent" in the left bar.