Plan your project accurate to the day: You can define a duration for your schedule tasks. This can be specified in hours, days, weeks or months.
In order to be able to change the duration of schedule tasks,
you must be in the "Project management" group in the project.
You will be able to find the training video for the article here soon.
Click Path:
- Workspace Planning > Select Project > Schedules > Open Schedule
- The schedule duration can now be changed in 3 ways:
- In the grid, double-click on the field in the Duration column of a task. You can then enter the desired duration.
- Double-click on the bar of the task or use the button in the upper right corner to open the navigation bar. In the first tab "General" you can now adjust the duration of the task.
- In Gantt you can move the mouse over a bar, click on the points at the end of the bar and lengthen or shorten the bar.
- If you change the end date of a task, the task duration is adjusted accordingly. Please notice: If you do so the constraint type "Finish no later than" is set.
- The duration is always defined in working days, working weeks, months or hours. Examples for the input:
- 4 Working days: 4D
- 2 Working weeks: 2W
- 3 Months: 3M
- 1 Hour: 1HR
- Important:
- If you enter 0D as duration, your task is displayed as a milestone.