Create a new schedule under consideration of holidays and templates.
To create a new schedule, you must be a member of the
"Project Management" team in the project.
Soon you will be able to find the training video for the article here.
Click Path:
- Workspace Planning > Select project > Schedules > "+ New" > Next
- First, holidays can be added or edited. Holidays are not considered working days and extend the duration of a task in the schedule accordingly:
- Under the tab Company Holidays you can click on "Import Company Holidays" to add the defined holidays from the company holidays.
- You can add more holidays under the Custom Holidays tab. To do so, select a period, enter a suitable description and click on Add Holiday.
- On the Selected Holidays tab you can see all the holidays added to the calendar and edit them.
- Click Next to add schedule templates:
- Select a template. Then select either all tasks or only some of them and click Save.
- The start date of the leading task(s) from the imported template is the same as the start date of the schedule. You can set the start date when creating the schedule or later in the schedule settings.